Management of competing water uses and associated ecosystems in Pungwe Buzi and Save Basin Transboundary drought risk climate resilient pilot project

Management of competing water uses and associated ecosystems in Pungwe Buzi and Save Basin Transboundary drought risk climate resilient pilot project

Project Details

Sponsor(s)

Budget

Implementing Partner(s)

Global environment Facility (GEF). International Union for Conservation of Nature (IUCN), Global Water Partnership Southern Africa

Period

2024

Location

Chimanimani

Status

About Project

Project Background

Fambidzanai Permaculture Centre (FPC) is implemented a drought and climate resilient demonstration project in the BUPUSA basins as a local delivery partner, on behalf of the Global Water Partnership Southern Africa (GWPSA) for the project: “Management of competing water uses and associated ecosystems in the Pungwe, Buzi and Save basins”. The project was implemented by the International Union for the Conservation of Nature (IUCN) and funded by Global Environmental Facility (GEF). The project’s main objective was to strengthen the management of transboundary water resources and connected ecosystems for sustained ecological benefits and improved resilience for riparian communities. GWPSA provided a Situational Analysis report which proposed implementable drought management interventions (small grants projects) in the selected drought hotspots within the Buzi, Pungwe and Save River (BUPUSA) Basin of both Mozambique and Zimbabwe.

Project Overview

The project established a solar powered garden that integrates sustainable agricultural practices, replaces an existing bush pump, and enhancing community access to water for irrigation and other domestic uses. This initiative will also include erecting a fence to protect the area from animals, ensuring both agricultural sustainability and community safety. The identified project site is loosely fenced with local resources and thus limiting productivity and the drudgery in use of pump for irrigation. The identified project site in Tagarirwa Village Ward 7 Bumba Area, as shown in figure 1 above. Project beneficiaries were supported with fruit trees to establish an orchard site diversification of income streams.

Key project components

The project established the following project components:

  1. Solar powered borehole
  2. 5000l water storage tank
  • 77 ha nutrition garden with a 535m perimeter fence
  1. Water points (14 garden taps and 3 community water points)
  2. Orchard site on garden perimeter for establishing fruit trees

Project Objectives

To improve access to water for the community through installing a solar powered borehole

The project installed a solar-powered water pump to improve water access for gardening while at the same time improving on the drudgery of the use of an existing manual water pump. A borehole capacity test was conducted to assess the yield and sustainability of water resources for the garden project. The results were highly positive, indicating an abundant water supply (8000ltrs/hour) that significantly exceeds the irrigation needs of the garden, with preliminary water quality tests confirming its suitability for agricultural use. These findings not only assure the sustainability of the garden project but also enhance community confidence and support to the whole development initiative

The project designates areas for livestock and community members to access water easily without depriving community members of the services they have originally been having at this water point. Three water points for fetching water and at the same points water troughs for drinking water to livestock were constructed and this ensured that needs were catered for the community members outside the project.

To improve access to food and nutrition through establishing a nutritional garden

The project promoted the production of horticulture crops and emphasised on a 3-star diet concept to improve access to food and as well as promoting consumption of balanced diets among project beneficiaries. In order to achieve this, the project constructed a fence around the garden to protect crops from domestic livestock and ensure production all year round. Pegging of the garden was done by Agritex and a total of area of 1.77 ha was earmarked for the garden.  A 1.8 m height diamond mesh wire was installed with one main gate and 4 small gates for access into the garden.

To promote adoption of sustainable agriculture practices

Implement climate-resilient agricultural practices that enhance food security and community livelihoods. Beneficiaries were trained on horticulture production using agroecology practices such as soil fertility management, integrated pest and diseases management, watershed management, fruit tree production and horticulture as a business. Beneficiaries were also trained on basics of financial literacy.

Project Design

Site selection

Under this project, a Situational Analysis report has proposed implementable drought management interventions (small grants projects) in the selected sites within the Buzi, Pungwe and Save River (BUPUSA) Basin of both Mozambique and Zimbabwe. The document has outlined hotspots, issues and impacts in the BUPUSA river basin. Therefore, Chimanimani being one of the areas highlighted in the situation analysis report, FPC together with key stakeholders selected ward 7 of Chimanimani district and specifically established the project in Tagarirwa village. Through the assessment and collective evaluation, the chosen garden site was considered a priority for several reasons among them, a guaranteed water sources for servicing both the garden and the community, availability of land and willingness of the landowners to cede back their land to local authorities, catchment areas of services and the potential limitations for garden establishment considering the timelines. The project is by the roadside of the highway to Chimanimani town and hence has a significant influence on passerby while the large influence is within the influence of Chief Mutambara area particularly local and surrounding villages up to the local business centre, Nhedziwa.

Site Validation

The garden site validation meeting was convened to assess and approve the proposed garden site. The meeting brought together key stakeholders such as Chimanimani RDC, Women Affairs, Social welfare and Youth affairs departments, ARDAS formerly AGRITEX, RIDA, Ward Councillor and representatives from the Chief Mutambara and Village heads to discuss the site’s suitability, address concerns, and collaboratively make decisions. The stakeholders physically visited the site and appreciate the dynamics of the conversion of the water systems from bush pump to solar water system. The garden site validation was a successful collaborative effort, resulting in the approval of the site with a shared commitment to addressing concerns and fostering community engagement. The stakeholders expressed enthusiasm for the upcoming gardening initiatives that aim to enhance local food security and community well-being. Recommendation from the stakeholders was however centred on the need of engagement of technical focal people to advise on areas that require technical expertise such as conduct of a borehole capacity test to inform further developments.

In addition, the local authorities also emphasised on the district standards on community garden which they indicated that it must be at least 2 hectares in size.  The availability of land size of 2ha and the capacity test results on the output of the water sources further cemented the selection of the garden site and confirm its further establishment.

ESMP & Screening Training

Environmental and Social Management Plan and participatory screening training of the local stakeholders was also done and was facilitated by team members from GWPSA. The participants were representative of all key community stakeholders and office bearers from Chimanimani RDC, Women Affairs, ARDAS formerly AGRITEX, RIDA, Ward Councillor and representatives from the Chief Mutambara and Village heads who have an influence on the project activities. Participants gained a comprehensive understanding of the key principles and objectives of Environmental and Social Management Plans, including their importance in project planning and execution. The sessions on participatory screening equipped participants with practical skills to facilitate community meetings and workshops, enabling them to better involve beneficiaries in decision-making processes. After the training, the ESMP screen tool was deployed, and stakeholders expressed their views and comments regarding the potential risks and challenges associated with the invention but however they all concurred to the fact that there is limited risk from the establishment of the garden and hence the establishment of can be supported to continue.

Stakeholder Engagements

The project prioritises engagement of key stakeholders at national, provincial, district and local level. Meetings foster unity of purpose and collaboration among key stakeholders such as Chimanimani RDC, Women Affairs, Social welfare and Youth affairs departments, ARDAS formerly AGRITEX, RIDA, Ward Councillor and representatives from the Chief Mutambara and Village heads. Diverse perspectives are being considered, leading to the incorporation of local knowledge into project programming. Transparent and fair selection processes prevented exclusion and ensured reach to vulnerable populations, maximizing the project’s impact. Support mechanisms for timely resolution of grievances are in place to enable continuous improvement based on feedback.

The project team engaged the local officials from the relevant government departments and local leadership from the conceptualisation phase of the project. Inputs and feedback on the development of the concept and the project idea was not a big challenge due to the existence of good working arrangements with all stakeholders in various other projects and engagements

During the inception meeting, after agreement on replacement of the bush pump with solar, the officials of RIDA cited the need for the decommissioning of the borehole since this was established through the China Aid. Indications were that the local office had to escalate the issue to the higher offices and seek approval for the process before engaging in the capacity test of the borehole. The process of get clearance by the local offices on the position of the borehole for the next step was stalled with delay in feedback from the local office on the decommissioning process resulting in delays in other developments.

The project team continuously engaged the stakeholders to push for the processing of feedback on the issue of the borehole clearance, but however upon the authorisation of the mechanisation of the borehole, all things were rolled to action.   The process was expedited by the presence of the project team on the ground and the availability of funds to spearhead the processes. The stakeholder engagement process leading to the approval of the borehole capacity was characterized by active participation and collaboration among community members, local authorities, and experts. The process facilitated transparent communication and built trust, allowing stakeholders to voice their opinions and contribute to decision-making.

The project team continuously engaged the local stakeholders and other key government offices at each stage of the development of the project. The Chimanimani Rural District council was actively engaged as they monitor their general guideline for the districts which indicates that a community garden in the district should be a minimum size of 2 hectares against our initially planned size of 0.75 ha sized garden. The department of ARDAS working with the department of environment and social services within the rural council were actively involved in the engagement of the local leaders and communities throughout all processes and planning meetings for the garden development. The Department of Rural Infrastructure development was also active engaged in the process of inspection of the borehole for feasibility and material quality assurance in line with installation of solar systems.

Borehole Capacity Test

The borehole capacity test was conducted to assess the yield and sustainability of water resources for the garden project. The process involved a thorough site assessment, followed by a controlled pumping test lasting 12 hours, during which flow rates and water levels were meticulously monitored. The results were highly positive, indicating an abundant water supply (8000ltrs/hour) that significantly exceeds the irrigation needs of the garden, with preliminary water quality tests confirming its suitability for agricultural use. These findings not only assure the sustainability of the garden project but also enhance community confidence and support to the whole development initiative. Overally, the successful capacity test laid a solid foundation for the project’s future development.

Project Redesigning

Pursuant of the standard sizes of community garden outlined by the Chimanimani RDC and consideration of the outcomes from the capacity test process, the project team engaged the beneficiaries on the redesign of the project to accommodate the recommendations. The beneficiaries deliberated on the issue and a recommendation was made to maintain the garden size and reduce in other cost but at least a concentration on ensuring availability of hardware components for water use at the garden site.  Resultantly the development on the garden was an output of participatory planning by the beneficiaries to prioritize on key interventions of the moment, sacrificing those of less priority. In this regard, the project now has the nutritional garden component supported by fruit trees for orchard site.

Beneficiary Selection Process

A transparent beneficiary selection process was conducted and spearheaded by the local community leadership. Priority during the selection process was given to old garden members, and vulnerable groups in the community which included the widowed, child headed families, ordinary women and the youth. The selection process gathered members from the areas around the garden site and the relevantly key stakeholders among them; Chimanimani RDC, Women Affairs, Social welfare and Youth affairs departments, ARDAS formerly AGRITEX, RIDA, Ward Councillor and Village heads. The screening (see annexed beneficiary selection tool) was done in a participatory manner which involved everyone with some community members stand out to voice out for other to be listed as beneficiaries.  A total of 26 more beneficiaries were added to the already existing garden members to make a total of 52 beneficiaries.

Signing of the Certificate of No Objection

Working with the recommendation of the council meeting on social services, the project team engaged the local leaders and villagers and deliberated on the issue of consent of use of the land in question of the garden and the size of the garden thereof as per the recommendations of the district committees on social services. The certificate of no objection (annexed) was signed, and the local leadership rallied behind the initiative and applauded the team for such an establishment which they feel will transform the lives of many and the landscape at large.

Pegging and Site Evaluation of the Garden

The ARDAs team working together with the local council and the project team were involved on the pegging and site evaluation for the establishment of the garden. The total area pegged amounted to 1.77ha in land size, falling short of the recommended 2 hectares due to limited space on the chose project site. The team also made recommendations of some conservation works to be established on site and the position of the main gate and the other smaller access garden. At least 4 small gates sites were established to ensure access to the garden from all areas since beneficiaries are drawn from areas around the garden from all areas

Erection of the Garden Fence

Contractors for the erection of the garden fence were engaged through a tender process as guided by our organisational policies. A total of 535 meters in perimeter was fenced with 1.5meters high diamond mash wire which also have 3 barbed wire strands on top making it inaccessible by both domestic animals and intruders. 5 gates were installed with one man gate and 4 pedal gates for access from all angles.

Solar System Installation

Contractors for the solar system installations of the garden fence were engaged through a tender process as guided by our organisational policies. A thorough site assessment was done together with the key stakeholders. The RIDA officials were engaged together with the public works technicians to ascertain and approve the standards and quality of materials used for the installations and all necessary clearances were obtained. A 3-horsepower submissible pump was installed on the site and operating alongside the existing bush pump and this is supported by an 8-panel solar system. To ensure easy maintenance, identified members of the community were taken through some maintenance training after the installation of the borehole.

Irrigation Design

After the borehole installation a water delivery system was also laid out on the ground with the trenching being done by the farmers. The laying process on all trenched surfaces was completed inclusive of some few areas which had some rock outcrops underground which were limiting the digging of trenches. Community water access points were also established together with at least one water trough for animal drinking where communities and livestock can access water.

Garden Design and Bed Allocation

The process of portion allocation was led by the local government extension officers through agreed sharing model which gave the previous landowners preference to retain portion of choice from their original section. The joining members were then randomly allocated sections through random picking of assigned numbers. The allocation process was deemed fair, and all parties were convinced of the fairness of the process and with no reservation or areas of potential conflict. Each beneficiary was allocated approximately 0.03 ha (300m2) and diverse bed designs were then established to demonstrate agroecology concepts, with a strong emphasis on soil and water conservation.

Crop Selection

The choice of crops should be based on nutritional value and local preferences. A 3-star diet concept was emphasised which focuses on a balanced approach to nutrition, emphasizing a variety of foods that are moderately healthy and sustainable. Balanced nutrition to consider core food groups including a mix of vegetables, fruits, whole grains, and proteins (e.g., legumes, nuts). Growing a range of vegetables and fruits to provide essential vitamins and minerals while keeping meals interesting. Leafy greens (spinach, kale), Root vegetables (carrots), and Legumes (beans, peas) were grown.

Agroecology Practices

The production in the garden is based on sustainable methods of farming. Agroecology practices and initiatives towards soil and water conservation, soil fertility management, pest and disease control in crops and livestock, and postproduction management techniques will be prioritised during implementation of this project. Farmers were trained ion the various agroecology concepts that will ensure their systematic production in the garden based in agroecology principles and with minimal external inputs in the production system. Natural resource management techniques and alternatives were also part of the training with focus being on watershed management to empower water point committees and the community t large on the significance of soil and water conservation.

SUSTAINABILITY PLANS

The members agreed on several factors that are aimed at ensuring sustainability among them the following key drivers of The Sustainability Plan

Establishment of the Garden Committee

A garden committee was established to run the affairs of the garden with the following leadership posts; Chairperson, Vice Chairperson, Treasure, Committee members (4), and at most garden advisors. The committee has equal representation for both genders and women given position of influence and decision making.

The section of the committee members was done through a secret ballot process which was overseen by the government extension officers as the officer presiding of the elections process.  A clear definition of roles and responsibilities of the committee members was also established and shared with all beneficiaries to ensure they are all policing each other on each other’s respective mandate.

Establishment of a Legally Binding Constitution

The beneficiaries independently drafted a constitution to govern the affairs of their garden. The constitution is to be endorsed by the Ward Councillor, local leadership and the local authorities. All garden members signed to the constitution as confirmation of agreement to the clauses contained therein.

Financial Management

The group treasurer has the responsibility of ensuring the funds are accounted for and the financial records are kept safe for presentation to all.

The role and responsibilities on financial management has been clearly segregated and has been made part of the constitution. The constitution also outlines how the funds for the group will be raised from penalties and contributions. The garden members established a local fund to facilitate minor repairs and maintenance as way of pressing their ownership of the whole development initiative.

Rules and Guidelines

Rules and expectations for participation were established and set with reference to the garden constitution.  Penalty fees for breaking rules and guidelines were also clearly defined with extreme cases calling for cancelation of membership as agreed. Guidelines for maintaining individual plots, including planting schedules, weeding, and harvesting are also part of the agreed clauses of the constitution.

CONFLICT RESOLUTION

Dispute Resolution Procedures: The project placed a strong emphasis on using traditional local leadership and indigenous methods and processes to settle disputes among participants. This ensures that issues are handled equitably and in a constructive manner through the trusted and old systems of local leadership.  The local leadership were also involved in the development process of the group constitution, and they are also signatories to the agreed clauses of the constitution.

Grievance Procedures: the constitution also clearly outlines the mechanism of launching grievances by garden members and   that Members can express their issues or grievances about garden management or procedures in a straightforward manner

CONCLUSION

This manual represents a guide for other future similar projects to be implemented in Chimanimani and other areas which may have the need for a similar project.   The manual has highlighted key focus areas that need to be considered when implementing such kind of work in Chimanimani including the key processes of stakeholder engagement which is a critical area that determines the future of the project otherwise if not properly conducted, it fails before reaching the implementation phase. If all process in this manual are properly followed, it can provide a significant step towards enhancing food security, improving livelihoods, and fostering community resilience in the face of climate change. Governance structures and conflict resolution mechanisms further ensures the sustainability and effectiveness towards achieving goals of the project.  Moving forward, continuous monitoring and adaptation is essential to maximize the project’s impact and ensure it meets the evolving needs of the community, ultimately contributing to the broader goals of environmental conservation and socio-economic development within the Chimanimani District.